Walk the Tamiami Trail promenade at The Bay on any weekday morning and you'll pass joggers, dog walkers, a couple of retirees doing tai chi near the Blue Pagoda, and construction fencing around what used to be the Van Wezel's parking lot. That fencing is the interesting part. By October, it comes down, and what opens in its place has a name that predates most of the people using the park by six decades.
The city is calling it The Plaza. Not Town Square, not some new marketing coinage dreamed up for a ribbon-cutting. The Bay Park Conservancy's chief operating officer, Diana Shaheen, told city commissioners this spring that the name is a direct callback to April 1964, when then-mayor Herschel Mayo dedicated that same patch of ground as Plaza de Santo Domingo, honoring Sarasota's sister-city relationship with the Dominican Republic's capital. Mayo's own words at the dedication described it as the hub of civic life in the city. Sixty-two years later, the Conservancy is reviving that framing on purpose, dropping "de Santo Domingo" but keeping the idea: this piece of the park isn't a scenic overlook, it's meant to be where Sarasota actually gathers.
That distinction matters more than it sounds like it should, because it tells you something about how The Bay has been built so far and what changes this fall.
Phase One Gave You A View. Phase Three Gives You A Reason To Come Back
When The Bay opened in fall 2022, its first phase leaned hard into spectacle: the Sunset Boardwalk, the Mangrove Bayou, sweeping lawns built for watching the water. It worked. As of mid-May 2026, the park's people counters had logged 1.15 million visits since opening, a number Mayor Debbie Trice called extraordinary for a city of roughly 58,000 residents. But a boardwalk is a place you visit. It's not a place you run errands past, meet a friend at, or cut through on the way somewhere else.
The Plaza is different by design. It sits at the midpoint of the Promenade, the 1,000-foot walkway along North Tamiami Trail that opened in 2025, flanked by 20-foot royal palms and connecting three buildings locals already have reasons to visit: the Blue Pagoda, the Chidsey Library, and the Municipal Auditorium. The Chidsey Library just picked up a 2026 AIA Florida Design Honor Award for historic preservation and restoration, credited to local firm Sweet Sparkman Architects. None of these are tourist attractions built for the park. They're civic buildings that predate The Bay entirely, and the new plaza is what finally stitches them together into something you'd walk to on purpose rather than stumble onto during a special event.
"As part of that dedication, Mayo said it is the very hub of our civic life."
That's the 1964 quote the Conservancy is leaning on, and it's a useful way to read what's coming. Phase 1 was a park you photographed. This next stretch is a park you use.
The Boat Ramp Tells The Same Story
If the plaza is the story for pedestrians, Centennial Park is the story for anyone who trailers a boat. The Bay's original build-out prioritized shoreline and lawns over launch capacity, and Manatee and Sarasota County boaters have felt that trade-off for four years. Phase 3 addresses it directly:
- A fourth boat ramp, increasing launch capacity by 33 percent
- Trailer parking capacity up 50 percent
- Rehabilitated north and east seawalls
- New floating day docks on the northeast side
- Restroom rehabilitation at the boat basin
None of this is glamorous. It's also exactly the kind of fix that only gets made once a park has proven residents actually use it hard enough to strain the existing infrastructure. The Bay wasn't under-built for boaters by accident. It was sequenced: stormwater and shoreline resilience first, then design amenities, and only once that foundation was in place did the Conservancy turn to expanding who the park physically serves. Founding CEO A.G. Lafley has been explicit about that order of operations, telling reporters the design process only gets to amenities and features after resilience and stormwater management are addressed.
What's Actually Opening, And When
The Bay Park Conservancy laid out a Phase 3 timeline this spring with real target months attached, not vague seasonal language:
| Target Date | What Opens |
|---|---|
| October 2026 | Town Square (The Plaza) and Van Wezel Way |
| February 2027 | Municipal Auditorium renovation, resilient shoreline |
| July 2027 | Centennial Park expansion (boat ramp, docks, seawalls) |
| September 2027 | First waterfront restaurant |
That restaurant line is worth sitting with. The operator is Venice Pier Group, the company behind Sharky's on the Pier and Fins at Sharky's, and it will occupy the former U.S. Coast Guard station site at the edge of the boat basin. Lafley told Sarasota County commissioners in April 2026 that construction starts next year with an opening in 2027. This isn't a chain testing the market. It's a Gulf Coast operator that already runs a restaurant concession for local government, having previously operated at the county-owned Snook Haven Park. If you've eaten at Sharky's, you already have a rough idea of what's coming to the boat basin, minus the beach and plus a view of downtown.
Why It's Taking This Long, And What "Half Finished" Actually Means
The Bay is a $200 million build-out split three ways: half from private philanthropy through the Conservancy, a quarter from the city, a quarter from Sarasota County, with the public portion funded by a tax increment financing district set up in fiscal year 2020. That district was originally projected to generate about $190 million over 30 years. By fiscal year 2026, redevelopment around The Quay and the Rosemary District had nearly doubled those projections, which is part of why the county has been cautious rather than eager about committing further bond funding this year, even while acknowledging the project's results.
The practical upshot for anyone who lives near the bayfront: the park is still, by the Conservancy's own accounting, less than half finished, with full completion targeted for the end of 2029. That's not a delay story. It's a sequencing story, and understanding the sequence is what separates "when is this finally done" frustration from actually knowing what to expect each year between now and then.
What This Means If You Already Live Near The Bay
If you've been treating The Bay as a place for sunset walks and the occasional festival, this fall is when that changes. The Plaza gives you a reason to walk through on a Tuesday rather than plan a special trip. The Promenade connects buildings you already had business at. The boat ramp expansion means launching on a Saturday morning should get less competitive by next summer. And the restaurant slated for 2027 means the boat basin stops being just a place to park a trailer and starts being somewhere to eat.
None of this requires you to do anything. It's simply worth knowing, if you're already calling this stretch of downtown home, that the park you've been walking past for four years is about to start pulling its weight as a neighborhood the way the buildings around it always have.
For more on what's shaping daily life and property values in downtown Sarasota this season, our Sarasota neighborhood guide tracks these changes as they happen, alongside our recent look at how the fall 2026 arts and dining season is reshaping the rest of downtown. If you're curious how bayfront improvements like these tend to show up in what a home is actually worth, S&J Hill Realtors has been watching this market long enough to tell you the difference between a headline and a home value. Reach out anytime, whether you're weighing a move or just want to talk about what's changing in your own backyard.